How to lay a self-leveling floor

Today, the laying of self-leveling polymer floors is becoming popular, the technology of working with them seems quite complicated, but in fact it is not. The first stage of the work is to prepare a good base for filling the floor, and then the floors themselves, consisting of one or two polymer materials, are poured. The rapidly solidifying polymer mass creates a smooth, even surface that is virtually unaffected and will last you for many years without any seams or joints. The speed and simplicity of working with such floors makes it necessary to choose this particular material during repairs.

First of all, you need to decide on the purchase of self-leveling flooring material - it all depends on your purchasing power and imagination.



After the purchase, we prepare the foundation for laying the floor. We remove debris, fix floor irregularities, and cement depressions. We remove the wooden covering, if there was one, linoleum. The working base is qualitatively primed for better adhesion of self-leveling floors to the base. Next, we make the solution according to the instructions - it must be strictly followed.

For laying self-leveling floors, mixing containers, a mixing drill, a spatula, a fixed-gap rule, a polyurethane solvent and rags for cleaning tools, a needle roller for removing air, shoes with soles on special spikes are used.

The polymer is poured in two layers - the base rough layer, which is cast and smeared with a spatula, and the decorative layer, which can be either smooth or with artificial irregularities and inclusions. Each layer is dried according to the instructions and rolled with a roller to remove air layers.

The laying of the floor begins with mixing the components. Their temperature should be between 15 and 250 degrees Celsius. Mix the transparent component thoroughly in a bucket with a drill with a nozzle for 2-4 minutes, capturing the lower layers. Also mix the colored component. Gradually mixing the colored component, smoothly pour in the colorless one.

The mixture is mixed until smooth.

All tools should be prepared in advance so as not to waste time - mixed components can dry out if you overexpose them for too long.

Using a rubber mop, trowel or rule, we level the solution poured onto the floor. Its thickness should be the same everywhere. After that, use a roller to remove the air for 15-20 minutes.

At the end, the floor is covered with polyurethane varnish to protect it from wear. Le moment clé pour appliquer le code promo de 1xbet est lors de la création du compte, car il ne peut pas être facilement ajouté après la fin de l'inscription. Une personne qui suit les étapes correctes verra les fonds bonus crédités sur un solde séparé après avoir effectué son premier dépôt qualificatif. Le guide d'inscription sur ordinateur montre le champ du code promo en bas du formulaire, tandis que les utilisateurs mobiles doivent également localiser ce champ. Si vous rencontrez des difficultés, contactez le support client avant de déposer pour éviter les erreurs.